Moynihan StationRSS

The new Penn Station, also called Moynihan Station, is a proposed renovation and overhaul of the current Farley Post Office at 8th Avenue and 33rd Street. The original proposal, made in 1993, called for the façade of the post office to be maintained, while the internal structure would be completely redesigned. That proposal was rejected in 2006 by the Public Authorities Control Board, at the urging of Assembly Speaker Sheldon Silver. However, under the Spitzer administration, the current chairman of the Empire State Development Corporation (ESDC), Patrick Foye, revived the discussions and formed “Plan B”.

This new plan, a joint effort between the city and State, Amtrak, New Jersey Transit, and the Metropolitan Transportation Authority, as well as developers Related Companies and Vornado Realty Trust, calls for a much larger project than originally envisioned. The current proposal calls for Madison Square Garden to be moved to the west end of Farley; the current Pennsylvania Station to be renovated and opened to light; and the superblock between Seventh and Eighth avenues and 31st and 33rd streets, to be turned into two to four office towers containing about five million square feet of office space. With their purchase of the adjacent Hotel Pennsylvania and Manhattan Mall, Vornado hopes to transform this large swath of midtown with thousands of square feet of class A office space.

Supporters of this new project include a wide range of interest groups. Many groups see the plan as a type of redemption for allowing the demolition of the old, and architecturally distinguished, Penn Station. Transportation groups are supportive of it because the plan will create a more efficient Penn Station with more capacity for Amtrak, NJ Transit, and the LIRR. Developers are supportive of the plan because they see the project as the key to opening the far west side of Manhattan to commercial development. In addition, the project is viewed as an important link between the potential developments of the Hudson Yards to the rest of Manhattan’s business district.

On February 2, 2007, ESDC signed a memorandum of understanding that extended the state’s option to purchase the Farley Building from the U.S. Postal Service. On March 30, 2007 the purchase was approved with the Port Authority paying $140 million of the $230 million purchase price. The remainder of the cost will come from private developers (The Related Cos. and Vornado) and a loan. Ultimately, the Public Authorities Control Board must still approve plans to turn the post office into Moynihan Station.

The ESDC formally initiated the public review process on October 23, 2007 when it released a draft scope of work for the project. Since that time questions have been raised about the financing for the plan. Originally, the cost of renovating the current Penn Station, located under the current Garden, was estimated to cost about $1 billion. The figure has now ballooned to $2.2 billion with another $1 billion required to expand the station into the Farley building. While $1.15 billion of that funding has been committed by the city, State, and private developers, there is still a major funding shortfall. Project supporters hope that the federal government will provide funding and that the private developers will commit additional funding, though it is not clear whether either will happen. The entire $14 billion project is also facing a weakening credit market and rising construction costs, which may make it difficult to finance such a large project. While Gov. Spitzer has remained publicly supportive of the project, Garden officials have not. In fact, it is believed that Garden officials are working on plans to renovate the current Garden because the plans for Moynihan station have dragged on so long. Without the Garden’s support, the viability of the entire project will be threatened.

Paterson and Schumer Agree on Moynihan Station

Governor Paterson has endorsed Senator Chuck Schumer’s idea of putting the Port Authority in charge of the Moynihan Station project. Mayor Bloomberg has openly opposed this idea. Paterson has said he will weigh both sides in reaching a final decision.

Send this story to a friend Printer friendly page

Governor Admits Money Shortage for Some Projects

Governor Paterson admitted publicly on Wednesday for that there might not be sufficient money for several New York City projects including Moynihan Station, Hudson Yards and the Jacob Javits Center. New York City is suffering from a real estate slump that has affected several other cities recently. The governor suggested that it might be necessary to have “either an individual or a committee oversee all the structural development in those particular areas” in order to overcome delays and budget shortfalls.

Send this story to a friend Printer friendly page

Developers for Moynihan Station Already Spent Millions

In a recent filing with the SEC, Vornado Realty Trust, a fifty/fifty partner with the Related Companies in developing Moynihan Station, has spent roughly $34.2 million on the project since being named the developer in 2005. The nature of the filing and a $23 million write-off, signals that in financial terms, Vornado believes the deal to remake Penn Station is dead.

Send this story to a friend Printer friendly page

Mayor Disagrees with Schumer's Plans for West Side

Following comments made by Senator Charles Schumer (D-NY) about the future development on Manhattan's West Side, Mayor Mike Bloomberg warned the Senator that "we set the cities priorities – they don't come out of Washington." Schumer and Bloomberg disagree on what essential elements are needed to get the Hudson yards project back on track. Schumer contends that Moynihan Station should be the top project, while Bloomberg has emphasized the extension of the No. 7 Subway line. The elected officials also disagree on who should spearhead the Moynihan Station project – Schumer would like to see the port Authority in control and Bloomberg disagrees.

Send this story to a friend Printer friendly page

Despite Recession, Schumer Favors More West Side Development

Even in the face of an economic downtown, Senator Schumer would like to see the Port Authority take over the expansion and renovation of Penn Station. He believes one of the City’s priorities should be to provide more office space. Mayor Bloomberg disagreed, saying that the City should be in charge of its own development priorities, though he would welcome funding from the State for Moynihan Station. Bloomberg does not support the Port Authority taking over the Moynihan Station project due to delays the agency has faced in the World Trade Center redevelopment.

Send this story to a friend Printer friendly page

Developers for Moynihan Station Committed to Garden Relocation

The Related Companies and Vornado Realty Trust have asked the city and the state to secure a loan that will finance moving Madison Square Garden to the Farley Post Office site which would allow for the larger project known as Moynihan Station to happen. However, if the Moynihan Station project falls through, the state and the city would be responsible for the costs of the new arena, totaling almost $1 billion. Under this proposal, construction of the new arena could begin soon while final approval for the larger project is still worked out. The Garden remains committed to renovating, not relocating.

Send this story to a friend Printer friendly page

Panelists Urge City to Concentrate on Moynihan Station

The New School’s Center for New York City Affairs held a panel on Wednesday to discuss the major projects in the City. Panelists, including Julia Vitullo-Martin of the Manhattan Institute and Comptroller William Thompson, emphasized that Moynihan Station needs to be a priority. Thompson asserted that there is money for the project, referring to $2 billion from the Port Authority. He also noted that because of the credit crisis, many of the City’s projects probably will not be realized.

Send this story to a friend Printer friendly page

Speculation Over New Priorities for Governor Paterson; Moynihan Station Could Get Funding Boost

As Governor Paterson is expected to appoint a new Executive Director for the Port Authority of New York and New Jersey, many are speculating how funding could be shifted away from the redesign of the PATH station at the former World Trade Center site to fill the funding gap needed to proceed with the Moynihan Station project. While this shift of money faces many political hurdles because it is from the federal government, some have said that it would be better utilized if allocated to the renovation of Pennsylvania Station since it has serves many more people daily. Governor Paterson has already offered his support to the Port Authority taking a lead role in the Moynihan Station plans.

Send this story to a friend Printer friendly page

Port Authority Willing to Take Over Moynihan Station Project

Port Authority Chairman Anthony Coscia, speaking at a breakfast forum, said that the agency was ready and willing to take over the stalled plans to build Moynihan Station. Coscia stated that the Port Authority would focus on the transportation aspects of the project, rather than the larger plan to package the new station with new office towers. The Port Authority believes improved and expanded transportation will spur economic development in the area and their financing and engineering expertise makes them well suited to take on the project. The decision to give the project to the Port Authority rests with Governor Corzine of New Jersey and Governor Paterson of New York.

Send this story to a friend Printer friendly page

Redevelopment Plans for West Side in Jeopardy

Due to a slowing economy, financial instability, logistical issues and setbacks with Penn Station and Javits Convention Center, Mayor Bloomberg’s overarching plans for redeveloping the West Side are in jeopardy. Several in the planning community believe that the City should use the delays as an opportunity to focus its efforts on rethinking the development plans for the area. Some urban planners argue that a less ambitious plan of establishing incremental developments toward the West Side would be more practical.

Send this story to a friend Printer friendly page

Vornado Supports Smaller-Scale Moynihan Station Plans

Steve Roth, the CEO of Vornado Realty Trust, wrote a letter to investors stating that he supports a smaller-scale redevelopment of Moynihan Station. Because Madison Square Garden announced last week that it would renovate in its current buildings, plans for a larger-scale station may be dead. Vornado is one of the co-developers for the smaller plan, which will create a new train station inside the Farley Post Office building. This plan has received many of the necessary approvals and already has the required funding.

Send this story to a friend Printer friendly page

Moynihan Station Project Could Continue Without the Garden Moving

Talks continue on the future of Moynihan Station despite the major setback that Madison Square Garden will renovate their facilities instead of relocating. Those familiar with the negotiation process have said that Moynihan Station could still become a reality even without the Garden relocating. A rezoning is still needed to make the project happen, however, newly-seated Governor David Patterson has yet to focus much attention on the project.

Send this story to a friend Printer friendly page

Renovation Plans Announced for MSG

Madison Square Garden, the second oldest NBA and NHL arena, announced plans for interior renovations that will reconfigure many of the concourses, lobbies, entrances, seating and concessions. According to executives from the Garden, the renovation work, totaling $500 million, can be done through building permits and does not need further public and city approval. With renovation on the horizon, plans for Moynihan Station are looking dim considering that the development is contingent on the Garden relocating.

Send this story to a friend Printer friendly page

Uncertainty Over Garden’s Decision to Renovate Leaves Many Parties Speculating

Various stakeholders involved in the Moynihan Station project are unsure how serious Jim Dolan, owner of Madison Square Garden is, on renovating the arena. Some speculate that Dolan is just using political maneuvers to put himself in a better position if and when discussion on Moynihan Station resume. If he does stick to his renovation plans, he must receive City Council approval. That could be difficult considering that Speaker Christine Quinn supports the Moynihan Station project and released a terse statement against the Dolan’s decision to renovate.

Send this story to a friend Printer friendly page

$20 Billion in Development At Risk Due to Slowing Economy

Due to the slowing economy, over $20 billion in development projects in the City could be scaled back, significantly delayed or even killed. The affected projects include Moynihan Station, Fulton Station, Atlantic Yards, Coney Island and the World Trade Center redevelopment. According to Robert Yaro, president of the Regional Plan Association, “We’re not going to throw in the towel on any of these projects, but less dramatic and less expensive designs may be needed.”

Send this story to a friend Printer friendly page

City Officials Maintain Hope That MSG Will Rethink Withdrawal from Moynihan Project

One day after Madison Square Garden’s announcement that it would be renovating its current space rather than waiting for the Moynihan Station project to move ahead, City officials are expressing optimism that they may be able to persuade the Garden to rethink its decision.

Send this story to a friend Printer friendly page

Garden will Be Renovated; Moynihan Station Plans in Limbo

The Dolan Family, owners of Madison Square Garden, announced that they will be renovating the current stadium instead of pursuing options to relocate. As part of the plan to expand and renovate the Pennsylvania Train Station, located below the Garden, the stadium will have to be moved. Some believe that the announcement was a ploy to further the Dolan’s position in the ongoing negotiations. The Garden agreed to relocate in 2005 but have become increasingly frustrated by the slow pace that the development plans have progressed. The pace has been set by a complicated negotiation process that involved many different parties, the slowing economy, and the lack of public financing. In recent weeks, there have been talks about having the Port Authority involved in the Moynihan Station project because they have the financially backing and expertise to do the work.

Send this story to a friend Printer friendly page

Senator Schumer Urges Port Authority To Intervene on Moynihan Station

Senator Charles Schumer (D-NY) is calling on the Port Authority of New York and New Jersey to get involved in the efforts to rebuild Penn Station. The Port Authority has about $2 billion in capital funds that it has not used. Schumer says that it is within the mission of the Port Authority to work on this issue, considering it’s a bi-state agency.

Send this story to a friend Printer friendly page

State-Level Turnover Could Have Impact on City Development Projects

The resignations of both former Governor Eliot Spitzer and Empire State Development Corporation (ESDC) head Patrick Foye have raised doubts about the New York City projects that the two were heavily involved in. Moynihan Station, which was already on shaky financial ground even with Spitzer’s support, could face even more troubles with uncertain leadership at the state level. The departures may also re-open the debates about what to do about the expansion of Javits Convention Center.

Send this story to a friend Printer friendly page

Governor’s Resignation Could Impact Major Projects

Governor Spitzer’s resignation is expected to impact the outcome of two major projects, Hudson Yards and Moynihan Station. The MTA anticipated designating a developer for the Hudson Yards site by the end of March. However, with a new governor entering office, some believe that it could take longer for a decision to be made. Additionally, the fate of Moynihan Station may also be in jeopardy as it is already facing budget constraints despite having Spitzer’s support. It is uncertain if David Patterson will be committed to supporting this project. Patterson’s decision to replace heads of certain state agencies could also affect the outcome of these projects.

Send this story to a friend Printer friendly page

Underground Pedestrian Tunnels Considered Around Moynihan Station

The City Planning Department recently announced to two Community Boards that it is considering a major network of pedestrian tunnels and above ground pedestrian walkways around Moynihan station as part of the renovations of Penn Station. The tunnels, which would be paid for by private landowners and developers, would connect the train station with Herald Square and with other subway stations in the surrounding area. These plans are in the preliminary stages, and would be included as part of the rezoning of the area.

Send this story to a friend Printer friendly page

Port Authority May Have Role in Moynihan Station Project

As plans for Moynihan Station have stagnated, Governor Elliot Spitzer has continued to work with the developers and Madison Square Garden officials to try to keep the project alive. Two transportation officials, speaking under the condition of anonymity, have said that Spitzer’s most recent plans to save the project may include involving the Port Authority, whose experience with large transportation projects and access to funds could help to overcome the project’s recent political and financial problems. While the project developers Vornado Realty Trust and Related Companies support the Port Authority’s inclusion in the project, the idea has its opponents, including the MTA, who would be competing with the Port Authority for funding, and the Empire State Development Corporation, who would have to cede some control over the project.

Send this story to a friend Printer friendly page

Moynihan Station Faces Pressures From Many Sides

Governor Spitzer’s grand plans for Moynihan Station are facing both financial and timing pressures. If the plan does not get commitments for funding soon, it could fall apart, leaving Penn Station untouched. The Governor is asking the federal government for $800 million and the state and city governments for $200 to $300 million more. Timing is also an issue, as Madison Square Garden has said that it wants to renovate if the plans for Moynihan Station do not proceed. If the Garden renovates rather than relocates, this would basically shut the door for further redevelopment of Penn Station, as the plan depends both on letting in light into the station and on transferring the air rights above it. If the current plans fall through, state officials are uncertain about what their next steps would be.

Send this story to a friend Printer friendly page

Governor Holds Off Sale of North Parcel Near Javits

Governor Eliot Spitzer has decided to hold off selling one of two parcels of land near the Javits Center that was intended to be used for the expansion of the Convention Center. The Spitzer Administration announced that a task force of elected officials, hotel and tourism executives would discuss the city’s future with trade shows and tourism. While plans to hold off the sale of the northern parcel were put on hold, the state is moving forward on efforts to sell the southern parcel of land to raise revenue for other major projects in the city.

Send this story to a friend Printer friendly page

Failure to Build Moynihan Station Could be Financial Trouble for Vornado

In an analyst report issued over the weekend by Morgan Stanley, the potential failure to rebuild Penn Station into Moynihan Station “would knock $11 off Morgan’s $94 price target for Vornado stock.” Reports about the potential failure of the planned redevelopment of Pennsylvania Station into Moynihan Station may have led to this conclusion by Morgan Stanley. Vornado Realty Trust is a 50% partner in developing the new train station and its surrounding areas. Negotiations for the project have been slowed because of rising costs and concerns from Madison Square Garden and other community groups. However, Governor Spitzer remains committed to the development.

Send this story to a friend Printer friendly page

Plans for Moynihan Station May be in Peril

The Moynihan Station project may have hit yet another snag. Financing problems have plagued the project in recent weeks and now the delays and rising costs may prompt Madison Square Garden to withdraw. According to the New York Times, Garden officials may announce plans to renovate the existing stadium rather than move it to the Farley building to accommodate the development of a new Moynihan Station on the Garden’s existing site. Governor Spitzer plans to meet with the developers and official from MSG next week to attempt to resolve the budgeting issues.

Send this story to a friend Printer friendly page

Governor Still Committed to Moynihan Station Despite Funding Shortage

Governor Eliot Spitzer restated his commitment to the development of Moynihan Station, despite a financial shortfall of over $1 billion. Spitzer reassured the city that there was "real progress” being made on this project, and it would not suffer the same fate of the now defunct plan to expand the Javits Convention Center. The Governor’s statement came a day after the Empire State Development Corporation announced it was still putting together the financing for the project.

Send this story to a friend Printer friendly page

Moynihan Station Costs Rising

Plans to rebuild Pennsylvania Station are becoming increasingly more expensive – the newest price tag is estimated to be over $3 billion according to Patrick Foye, Chairman of the Empire State Development Corporation (ESDC). The costs include creating a more open and airy Penn Station and to extend the station on to the Farley Post Office site, but does not include rebuilding Madison Square Garden. According to Foye, the state currently has about half of the money it needs to start the process and is hoping to raise the rest by seeking funding from the federal government, New Jersey, and more from private developers. The state is expected to announce a construction plan for the project in the spring. Redevelopment of Moynihan Station will have the same effect on the value of the West side of Manhattan as Grand Central Station did on the value of the East Side, according to Foye.

Send this story to a friend Printer friendly page

Major Projects Face Cost Increases and Schedule Delays

The Javits Center and Moynihan Station projects are experiencing major delays as a result of increasing costs. Governor Spitzer entered office last year with plans to double the size of the existing plans for the Javits Center. As the project’s costs grew to $5 billion, the entire project had to be revised. The latest proposal is to build a new convention center in Queens, which would renew the ULURP process. Moynihan Station is also behind schedule due to a growing budget. It was first introduced in 1997, scheduled for completion in 2002 at a cost of $455 million. Construction has not yet begun and the most recent estimated cost is $14 billion. New expansion plans are being proposed and the original plans have changed extensively.

Send this story to a friend Printer friendly page

Stringer Proposes Bike Paths and Walkways for 33rd Street

Manhattan Borough President Scott Stringer is proposing to widen sidewalks, develop new bike lanes, and eliminate parking on West 33rd Street. The paths would connect Broadway to Hudson Yards, passing by the new Moynihan Station. Stringer’s plan, which he will announce at the public hearing on Moynihan Station, is supported by Regional Plan Association and Transportation Alternatives.

Send this story to a friend Printer friendly page

Moynihan Developers Hold Public Hearing, Woo Macy’s West

The developers of Moynihan Station are in the early stages of trying to lure Macy’s from its historic home at Herald Square into a new, glass-enclosed mall in the train station. Although the developers have not released a rendering of the station’s new look, they did release a conceptual plan on Nov. 29. The entire project is expected to cost $14 billion, which could include public investment of over $1 billion. The city and state are proposing a rezoning that will create 6.3 million square feet of transferable development rights, to be used in a 20-block area around the new station. There will be a public hearing today to discuss the current proposals on the development of Moynihan Station.

Send this story to a friend Printer friendly page

Friends of Moynihan Station Urge Public Input

With the anticipation of the Moynihan Station design renderings to be released next Thursday, Friends of Moynihan Station are urging that New Yorkers have input in the planning process.

Send this story to a friend Printer friendly page

New Penn Station Plans Unveiled

Governor Spitzer announced his plan for Moynihan Station, the new Madison Square Garden and the surrounding area. The plan includes moving the Garden to the old Farley Post office, building two new skyscrapers, and creating a major retail hub in the renovated Penn Station. The state’s plan also proposed rezoning the area for commercial and residential development, and creating 4.3 million square feet of transferable development rights.

Send this story to a friend Printer friendly page

First Step in Environmental Assessment Set for Remake of Penn Station

The state is expected to release the "draft scope of an environmental impact statement" today for the remake of Pennsylvania Station. Many believe that the state has been working to develop a cohesive plan for the project that involves many different interests, including Amtrak, the MTA, New Jersey Transit, the developers, Madison Square Garden, the city and the surrounding community. The release of the EIS is the first public action for Governor Spitzer's administration on the project. The current proposal would move the Garden to the old Farley Post Office and disperse new development throughout the area.

Send this story to a friend Printer friendly page

Garden Owners Ask For Alterations to the Farley Post Office

The owners of Madison Square Garden have stipulated that they must be able to make major alterations to the James A. Farley Post Office building before they agree to move the Garden to the building's western section. Since the Post Office is landmarked, certain changes could put its tax credit status in danger. The National Park Service has yet to assess the impact of the proposed modifications. The Empire State Development Corp. (ESDC) is currently working on a supplemental environmental impact statement for the plan.

Send this story to a friend Printer friendly page

Development Plans May Change for Proposed Farley Station

The Empire State Development Corporation (ESDC) is looking to shift away from building two large office towers where Madison Square Garden currently is and instead is hoping to disperse office space around the Midtown area. This change, according to Pat Foye, Chairman of the ESDC, "will mean less disruption to commuters, fewer financial risks, and it will tie the development around Moynihan Station to the demands of the market." The state is still considering the $900 million plans.

Send this story to a friend Printer friendly page

Recruiting of Federal Funding Continues for Moynihan Station Project

There has been a continued effort by Vornado Realty Trust and the Related Companies, the developers of the Moynihan Station project, to gain additional federal support to offset costs by the state and the developers. Through lobbying efforts, the developers have targeted specific legislative avenues for increased funding. The state continues to work on developing this project and the environmental review process could begin shortly according to those briefed on the plans.

Send this story to a friend Printer friendly page

Regional Plan Association Calls for Moynihan Station to Get Air Rights

The Regional Plan Association has recommended that the redevelopment of Penn Station include wider concourses and street entrances and include real-time train information to riders. Such an overhaul may require that nearby sites transfer their air development rights to Vornado Realty Trust and the Related companies, the developers in charge of the renovation.

Send this story to a friend Printer friendly page

Plans for Moynihan Station Revived

The plan to relocate Penn Station and Madison Square Garden and create new towers, which was seemingly killed in December 2006, appears to be back again. Two of the city’s largest developers plan to unveil new plans for Moynihan Station in the upcoming weeks. Both Governor Spitzer and Mayor Bloomberg support the plan.

Send this story to a friend Printer friendly page

Property Values Rising Rapidly in Times Square, Herald Square

Property values around Times Square and Herald Square have been experiencing rapid appreciation, even doubling in periods as short as a few months according to some sources. The price appreciation appears to be driven by demand for space by higher-quality and higher rent retail tenants, new office and residential projects, and meaningfully, the anticipated development of the new Moynihan station. This article describes many of the expected real estate transactions in the area which are delivering such high levels of profit.

Send this story to a friend Printer friendly page

Purchase of Farley Post Office First Step Towards New Transportation Hub

The purchase of the Farley Post Office was the first step in new transportation hub designed to deal with congestion and growing traffic. Originally, plans called for Moynihan station to be completed in 2010 but delays have made this schedule much less certain. NJ transit is expected to pay $2.3 million for a 99-year lease of the new station plus construction costs in return for exclusive control of the new rail station. NJ Transit chief has stated that he would like to complete Moynihan Station before the Hudson River Commuter Train Tunnel. Construction on the tunnel is expected to begin in 2009 and be completed in 2016.

Send this story to a friend Printer friendly page

Purchase of Farley Post Office Completed

Purchase of the James A. Farley Post Office by the Empire State Development Corp was completed on Friday, March 30th, a week after the financing plan for the purchase was approved. The Port Authority paid $140 million of the $230 million purchase price, with the remainder coming from private developers (The Realted Cos. and Vornado) and a loan. Purchase of the Post Office and construction of the new Moynihan Station is expected to reduce traffic at the congested Penn Station and spur economic development on the west side of Manhattan.

Send this story to a friend Printer friendly page

City Hall Appoints Director of Urban Design

In an effort to maintain the integrity and vision of the many development projects currently underway in New York City, the Department of City Planning has created a new department focusing exclusively on urban design and has appointed Alexandros Washburn as its head. Washburn’s previous experience includes serving as public works advisor to Senator Moynihan and as the president of the Pennsylvania Station Redevelopment Corporation where he oversaw plans to create Moynihan Station. Washburn’s appointment has been highly lauded, and he brings to his role a commitment to designing cities which reflect not only architectural aesthetics but the lives of its citizens, mixing the necessary creation of new developments with an effort to maintain city vibrancy and neighborhood authenticity.

Send this story to a friend Printer friendly page

Financing Plan for Moynihan Station Gets Approval

The Public Authorities Control Board approved the financing plan which will allow the state to purchase the Farley General Post Office as part of the plan to create the new Moynihan Train Station. The approval by the state panel was an important step in making the long anticipated Moynihan Station a reality. The plan will now allow the ESDC to take out a $35 M loan in order to meet the purchase price of $230 million. When completed the Postal Service will continue to use about 18% of the new Moynihan Station.

Send this story to a friend Printer friendly page

Moynihan Station Project Expects Approval

According to Newsday, the state's Public Authorities Control Board is expected today to approve $320 million of state financing for the acquisition of the Farley Post Office in conjunction with plans for the Moynihan Station project. Sources close to Speaker of the Assembly Sheldon Silver relayed that he would support the financing, signaling a dramatic reversal from his vote to reject the proposal last year under then Governor Pataki. The Moynihan Station project would transfer the rail hub at Penn Station to the Farley Post Office to the west as well as add commercial and retail space to the facility.

Send this story to a friend Printer friendly page

Step Forward Towards Moynihan Station

The Empire State Development Corp (ESDC) expects to close on purchase of the Farley Post Office this spring for $230 million as part of the plan for creation of the new Moynihan station. The purchase is being completed five years after Governor Pataki originally negotiated the deal. Port Authority will cover the majority of the price itself.

Send this story to a friend Printer friendly page

4 Office Towers Considered Near Farley Post Office

Real estate company Brookfield Properties unveiled a proposal to build four office towers to the south of the Farley Post Office, the site considered for the Moynihan Train Station. According to the company, the towers will occupy 4.7 million square feet total with two towers on the east side of the plot with 4 million square feet and two towers on the west side with 700,000 square feet. No anchor tenant has been announced for the proposed office space but much speculation abounds about the effect of plans for the Moynihan Station on surrounding properties.

Send this story to a friend Printer friendly page

Major Financial Company Weighs Departure from World Financial Center

Financial management company Merrill Lynch & Co. is considering leaving its current location in the World Financial Center because of what the company perceives is an obsolete space for modern trading. The company is considering several options, which include leasing space in one of the office towers being developed on the World Trade Center site by Larry Silverstein or establishing a headquarters at the Hotel Pennsylvania, owned by Vornado Realty Trust across from the existing Penn Station. Brookfield Properties Inc., Merrill Lynch's landlord at the World Financial Center, is attempting to keep the company there by proposing the creation of a modern trading floor.

Send this story to a friend Printer friendly page

ESDC to Purchase Farley Post Office for new Moynihan Station

The Empire State Development Corporation (ESDC) has announced its plans to buy the Beaux Arts building from the U.S. Postal Service as the first step in its plan to create the new Moynihan Station. The state is still in negotiations with the two private developers who are expected to take part in the project over their financial contribution. The ESDC was able to extend its option to purchase the post office for $230 million from Dec. 2006 until end of March 2007, and now plans to take advantage of that opportunity.

Send this story to a friend Printer friendly page

ESDC to Study Moynihan Station Plans

The Empire State Development Corporation has approved a $500,000 environmental impact study to determine the feasibility of plans to move Madison Square Garden one block west to the annex of the Farley Post Office, making the post office the Moynihan Station transit hub and leaving existing Penn Station to renovation and space for office towers. The ESDC did not consider the proposal by developers Vornado Realty Trust and Related Companies to create office towers when they approved the plans last year. A draft for the general project plan is expected in four to six months, at which time public review will begin.

Send this story to a friend Printer friendly page

Manhattan Borough President Highlights Moynihan Station

In his first ever State of the Borough address, Manhattan Borough President Scott Stringer placed the expansion of Penn Station into Moynihan Station as his top goal for 2007. The Moynihan Station Project, delayed at the end of Governor Pataki's term, is currently under serious consideration by Governor Spitzer. Stringer said that the Moynihan project would not only lessen congestion and improve the feel of the area, but would also serve as a foundation for transportation planning in the entire region.

Send this story to a friend Printer friendly page

Manhattan Borough President To Address Key Priorities

Manhattan Borough President Scott Stringer is expected to address his key priorities for 2007 in Monday’s State of the Borough Address. Stringer has stated that Monihan Station tops his project priorities, and that he also plans to focus on issues of affordable housing and improving city transportation. The Borough President is also expected to mention Governors Island as an area of exciting new development.

Send this story to a friend Printer friendly page

Moynihan Station Plans Back on Track

The fate of plans to redesign the area of Penn Station was largely uncertain at the end of former Governor Pataki's term in office. This article in the New York Observer details how current Governor Spitzer's new chairman of the Empire State Development Corporation (ESDC), Patrick Foye, has revived the discussions, enlisting the services of Amtrak, New Jersey Transit, and the Metropolitan Transportation Authority, as well as developers Related Companies and Vornado Realty Trust. On the table is "Plan B," an effort to redesign Penn Station, relocate Madison Square Garden to the west of Farley Post Office, and create an office tower "superblock" between Seventh and Eighth Avenues and 31st and 33rd Streets. Sources close to Spitzer say that the new plan for the area is a top economic development priority of the administration.

Send this story to a friend Printer friendly page

Large Developments Underway at Hudson Yards

Sparked by the rezoning of Hudson Yards in 2005, the area currently has 5 million square feet of new housing under construction. Several new hotel projects and potential office buildings are also in the planning stages. Along with the rezoning, redevelopment is also being encouraged by the extension of the No.7 subway line and potential construction of new Moynihan Station. Prospective office space developers have some concerns about how competition with new construction at Ground Zero could reduce the number of available tenants.

Send this story to a friend Printer friendly page

Vornado Finalizes Purchase of Manhattan Mall

Vornado has closed on its acquisition of Manhattan Mall on Sixth Avenue for $689 million dollars. Vornado also owns the Pennsylvania Hotel across the street and a large portion of the office space in nearby Penn Plaza. Vornado is one of the developers involved in plans to redevelop Madison Square Gardens and the Farley Post Office into Moynihan Station.

Send this story to a friend Printer friendly page

Deadline for State to Buy Farley Post Office Passed

New York missed the deadline to buy the Farley Post Office, which passed on December 31, 2006. Charles Gargano, then-chairman of the state’s Empire State Development Corporation, had attempted to extend the buying option at the end of then Governor Pataki’s term in office. Governor Spitzer’s office has continued negotiations, however. A spokesperson for the United States Postal Service said that they had no other plans to sell the building after the state missed the December 31 deadline. The Farley Post Office is a central piece of an ongoing proposal to construct Moynihan Station in the post office, as well as transfer parts of Madison Square Garden farther west.

Send this story to a friend Printer friendly page

Hotel Pennsylvania to Become Office Space, Station Plans Continue

The Hotel Pennsylvania, which opened in 1919 and is located on Seventh Avenue across from Penn Station, will be replaced by 2.5-million-square-feet of office space by 2011, according to Vornado Realty Trust. The hotel’s conversion to office space signals imminent change in Midtown, as Vornado and Related Companies, two firms charged by the state with development proposals for the new Moynihan station, continue to discuss proposals for the station. While the project to convert Farley Post Office into the new Moynihan station is stalled, both companies are pushing for a larger project to put a new Madison Square Garden on the Ninth Avenue end of the post office.

Send this story to a friend Printer friendly page

Request for Deadline Extension on Moynihan Station

With only three days left before the current offered for the Farley Post Office expires, the Pataki administration is hoping to get the deadline extended to provide additional time to raise funding. Currently the state has the ability to buy the Farley Post Office for $230 million from the federal government, but the offer expires at the end of 2007. The post office covers two city blocks and is central to the plans for the proposed transportation hub.

Send this story to a friend Printer friendly page

Management Company Hired to Oversee Transportation Developments

NJ Transit has hired CM Consortium to manage its $7.2 billion “Access to the Region’s Core” plan, hoping that the firm can help keep plans within budget and built in a timely manner. CM Consortium will oversee three engineering firms (The Partnership) who have already been awarded contracts to create designs for the proposed Hudson River commuter train tunnel and new Moynihan Station. NJ Transit hopes that construction on the projects could begin in 2009 and be completed by 2016.

Send this story to a friend Printer friendly page

Movement on Moynihan Station Not Expected Soon

Democratic speaker of the Assembly, Sheldon Silver, has apparently refused to appease the wishes of outgoing Governor Pataki to place Moynihan Station plan on the agenda of next week’s Public Authorities Control Board (PACB) meeting. The $900 million proposal to convert the landmark Farley Post Office into the Moynihan Train Station will likely be taken up next year by incoming Governor-elect Spitzer. Pataki had hoped to strike a compromise with the state legislature before leaving office.

Send this story to a friend Printer friendly page

Gov. Pataki Using Development Projects in Deal for Pay Raises

Governor Pataki is reportedly interested in striking a deal with the state legislature over their proposed first salary hike since 1999. While Pataki is opposed to raising the salaries of state lawmakers, he is apparently willing to strike a compromise if the legislature agrees to pass his six-item wish list. This list includes approval of the Atlantic Yards Plan and Moynihan Station.

Send this story to a friend Printer friendly page

Developer Says Construction On New Madison Square Garden To Start In 2008

Stephen Ross, a major real estate developer, has predicted that construction will soon begin on a plan that involves building a new Madison Square Garden inside the Farley Post Office building, renovating Penn Station, and erecting office towers in the surrounding area. Pataki administration officials say that Mr. Ross's projections are wildly optimistic. The administration is hoping to revive the plan to convert the Post Office building into a train station.

Send this story to a friend Printer friendly page

Pataki Eager To Close Deals Before Leaving Office

Sources close to the Pataki Administration say that the current governor is willing to broker deals with state legislators in order to finalize some development priorities. In particular, the governor wants to exit the job with a final agreement on a $900 million plan to build Moynihan Station in the space of the Farley Post Office. In order to finish the deal, Pataki will have to negotiate with Democratic speaker of the Assembly, Sheldon Silver, who has already blocked the governor’s plan as a member of the Public Authorities Control Board.

Send this story to a friend Printer friendly page

Vornado Realty Trust Purchases Manhattan Mall on Sixth Avenue

Vornado Realty Trust, a proponent of redevelopment of Farley Post Office/Moynihan Station and Madison Square Garden, purchased the one-million-square foot Manhattan Mall on Sixth Avenue between 33rd and 32nd Streets for $689 million from Argent Ventures. Vornado already owns the 1.4-milliion-square foot Pennsylvania Hotel across from Manhattan Mall, near Penn Station.

Send this story to a friend Printer friendly page

Chairman of ESDC Frustrated about Moynihan Station Project

On Wednesday the Chairman of the Empire State Development Corporation (ESDC), Charles Gargano, expressed frustration about the state of the new Moynihan Station project. Gargano intimated that the current impasse in the proposal is due more to the actions of the Public Authorities Control Board than to the RFP (request for proposals) that the ESDC sent out to developers.

Send this story to a friend Printer friendly page

Gov.-elect and Mayor Meet: Development Projects Mentioned

The Mayor of New York City, Michael Bloomberg, and Governor-elect, Eliot Spitzer, met on Friday for a private breakfast to display their friendly political relationship. While the governor-elect and mayor maintained that they would not always agree on key policy issues, the two expressed the likelihood of great agreement on most projects. On the issue of Moynihan station, both expressed the need to move the project forward. Spitzer maintained that “open issues” exist with regard to the project, however. The redevelopment of Ground Zero and the 2nd Avenue subway were also discussed.

Send this story to a friend Printer friendly page

Stephen Ross to Chair Real Estate Board of New York

Chairman and CEO of Related Companies, Stephen Ross, will be the next Chairman of the Real Estate Board of New York (REBNY). Ross will serve a two-year term at the Board, which begins on January 1, 2007. Ross, whose Related Companies has been a developer on many large scale projects including the Time Warner Center, will help to influence many municipal matters concerning land use, tax policy, city planning, and zoning.

Send this story to a friend Printer friendly page

NJ Transit Plans New Entrance to Penn Station

New Jersey Transit announced plans to build a new entrance at Penn Station that will open onto 31st Street and Seventh Avenue. The new entrance will not interfere, however, with plans for the new Moynihan Station. The entrance will reduce the pedestrian congestion caused by the major entrance at 32nd Street and Seventh Avenue, serving both Madison Square Garden and the railways beneath the entrance. The new NJ Transit entrance will assist the 50,000 passengers who use the concourse, which serves the trains traveling to and from New Jersey. The cost of the program is $12 milllion and is expected to be finished in 2008.

Send this story to a friend Printer friendly page

Architects Present Plans to Penn Station Developers

In late October four architectural firms: Lord Norman Foster, Cesar Pelli, Kohn Pedersen Fox Associates, and David Childs of Skidmore, Owings & Merill introduced plans to the Related Companies and Vornado Realty Trust, developers of the Penn Station area redesign. Preliminary designs feature two or four towers of differing elevations that surround Penn Station. The basic hope is to make the five-block section of midtown west a pedestrian and commuter-friendly, open-air center. The status of the proposals remains uncertain.

Send this story to a friend Printer friendly page

Next NY Governor Has Big Development Challenges Ahead

Eliot Spitzer or John Faso, New York State gubernatorial candidates, will face a laundry list of state needs upon the outcome of Tuesday’s election. Particularly daunting is the complex combination of development projects: World Trade Center Site, Moynihan Station, and Madison Square Garden. The New York Sun assesses the biggest challenges facing the candidates.

Send this story to a friend Printer friendly page

Major Building Planned For West Side

A New York developer is planning a new office development across the street from the proposed Moynihan Station project. According to the New York Post, Brookfield properties intends to build a platform over an exposed rail yard between Ninth and Tenth avenues creating a site that could support up to 4.7 million rentable square feet.

Send this story to a friend Printer friendly page

Moynihan Station: The Silver Version

After blocking approval of the current plan to turn the Farley Post Office Building into Moynihan Station, Assembly Speaker Sheldon Silver said a new version of the plan could be approved within six months. The Silver-endorsed plan proposes moving Madison Square Garden across Eighth Avenue and into the rear half of the post-office building.

Send this story to a friend Printer friendly page

A Simplified Design For Moynihan Station

According to the New York Times, the most current design for the stalled Moynihan Station has been pared down from earlier iterations. Starting in 1999, three successive design teams have created visions for the former post office. While one critic calls the latest design an “uninspired matchbox covered with a glass roof,” officials say the simplicity will result in a gain in space for passengers.

Send this story to a friend Printer friendly page

Mayor Questions State Board

Mayor Bloomberg has criticized the state board that recently rejected the Moynihan Station project. This is the same body that voted against the proposed Jets stadium on the West Side, one of the Mayor’s pet projects. The Mayor questioned the constitutionality of one body having so much power in State government.

Send this story to a friend Printer friendly page

The Political Battle Over Moynihan Station

New York Magazine analyzes the political maneuvering underlying the battle over Moynihan Station. With the Governor, Assembly Speaker, and owners of Madison Square Garden all interested parties, the magazine notes that there are "no shortage of agendas."

Send this story to a friend Printer friendly page

Moynhihan Station: Dead? Or Simply On Hold?

The Pataki administration has declared the $900 million Moynihan Station project “dead” after State Assembly Speaker Sheldon Silver refused to endorse it. The project did not receive required approval from the state’s Public Authorities Control Board. The New York Times reports that the project could be revived under the next governor’s administration, perhaps even reconfigured to include the proposed relocation of Madison Square Garden. In the aftermath of yesterday’s events, a Pataki administration official referred to Silver as “sorry-minded politician,” while Silver said the administration was only concerned with “photo-ops and cornerstones.”

Send this story to a friend Printer friendly page

Silver Rejects Moynihan Station

Assembly Speaker Sheldon Silver refused to support the Moynihan station project Wednesday, saying he feels the $900 million project doesn't meet the needs of the surrounding neighborhood. In response, Governor George Pataki has asked that the vote on the project be postponed again until another unspecified date.

Send this story to a friend Printer friendly page

Pataki Prepared To Cancel Moynihan Project

Governor George Pataki has issued a letter saying that if the Moynihan Station rail terminal project is not approved on Wednesday, he will recommend tossing out the current plan at the risk of losing $130 million in promised federal funding.

Send this story to a friend Printer friendly page

Another Moynihan Delay

The fate of the Moynihan Station project remains uncertain after a state panel again failed to approve the $900 million project. The three-member Public Authorities Control Board did not take a scheduled vote last Friday on the proposal to convert the Farley post office into a train station. Governor Pataki and Assembly Speaker Silver remain at odds over the financing and scope of the project.

Send this story to a friend Printer friendly page

Silver On Moynihan Station: More Needed For NYC Residents

Assembly Speaker Sheldon Silver has said that he opposes the current form of the plan for Moynihan Station because it would benefit only commuters from New Jersey. Silver is supporting a plan to move Madison Square Garden into the back of the Farley Post Office Building and to renovate Penn Station.

Send this story to a friend Printer friendly page

Vote Set On Moynihan Station

After about eight years of planning, Governor Pataki and his development team have pushed to start construction on Moynihan Station before they leave office at the end of December. The $900 million project would remake the Farley Post Office building on Eighth Avenue between 31st and 33rd Streets into a transit hub. The developers for the project have also introduced an ambitious plan to move Madison Square Garden to the west side of the Farley building.