QUICK LINKS
World Trade Center Redevelopment
Almost immediately after the attacks of September 11, 2001, plans began for the redevelopment of the 16 acre site of the former twin towers. Just months before the attack, the Port Authority of New York and New Jersey (PANYNJ), the owners of the site, reached an agreement with developer Larry Silverstein for a 99 year ground lease of the site. This agreement technically left Silverstein with the right to develop the site in the wake of the attacks. However, shortly after 9/11, New York State created The Lower Manhattan Development Corporation (LMDC) as a subsidiary of the Empire State Development Corporation. LMDC was charged with coordinating the reconstruction of the World Trade Center site and administering the bulk of the public sector funding allocated for recovery. In addition, LMDC was tasked with engaging the public with regards to the commercial and memorial developments on the site.
Daniel Libeskind’s master plan was selected through a design competition organized by LMDC for the site in 2003. Together with Silverstein’s architectural firm of Skidmore, Owings and Merrill, a development plan for the site emerged in 2004, which included the 1776 foot tall Freedom Tower. Also in 2003, LMDC sponsored a design competition for the World Trade Center Memorial. The winning design, “Reflecting Absence” by Michael Arad and Peter Walker, was chosen in January 2004.
Construction at the site stalled for several reasons. The most basic was the competing visions for the site that were held by the various stakeholders – victim’s groups, Mr. Silverstein, the Port Authority, the Governor’s office, and LMDC. Many victims groups thought more money and attention should be spent on the memorials than was proposed. Many of the stakeholders, including PANYNJ and some in LMDC, saw the design as a chance to improve upon the condition of Lower Manhattan by reintroducing parts of the street grid and constructing a world-class transportation facility. Some, including Mayor Bloomberg early in the design process, thought that the design should have placed more emphasis on housing and community facilities, instead of office space. They claimed that Lower Manhattan actually had a glut of office space and that even before the attacks, many former office buildings were being converted to housing, reflecting the needs of the current market.
In 2006, the Port Authority reasserted its dominance in the reconstruction process and was able to reach a deal with Mr. Silverstein in which full construction of Mr. Silverstein’s buildings would be completed in 5 years. Before the 5 year clock could begin, however, the Port Authority had to complete the excavations for several sites. Originally scheduled to be complete by the end of 2007, PANYNJ could not finish the excavation work until February 2008 and was forced to pay Mr. Silverstein a fine for the delay. As part of the agreement, Mr. Silverstein ceded rights to develop the Freedom Tower and Tower Five (which will be located on the site of the Deutsche Bank building) in exchange for financing from the sale of Liberty Bonds for towers Two (200 Greenwich St), Three (175 Greenwich St), and Four (150 Greenwich St), which are considered to be the most marketable properties of the site.
Another reason for delay at the site was that the New York City Police Department requested modifications to the Freedom Tower’s design to improve security. Further delay was caused by the refinement of the design and cost of the memorial. Originally designed as a more barren plaza, the current design includes vegetation as well as additional cultural buildings. This process pushed back the anticipated completion of the memorial to 2011 from 2009. The lack of a comprehensive insurance settlement from the attack further frustrated construction. Though several insurers had paid a cumulative $2.55 billion, the outstanding insurers, that owned the most liability, did not reach a settlement until more than 5 years after the tragedy. In May 2007, with the help of the State Insurance Commissioner and the Governor, the outstanding insurance claims were finally settled for another $2 billion. With that major piece of the financing taken care of, the pace of construction activity quickened at Ground Zero.
In late 2007, Westfield, a company specializing in retail development, signed an agreement to develop a major portion of the retail at the WTC site. While some of the retail will be inside, a large portion of it will be at street level. This is in marked contrast to the former development in which most of the retail was located underground. Having active street level retail was a goal of many residents of the community. In addition, the City and State are in negotiations to lease out major portions of the new facilities’ office space. By agreeing to leases now, before construction is complete, the governments hope they can secure favorable lease rates. Such pre-leases would also benefit Mr. Silverstein who would have some guaranteed leasing income.
While these developments were occurring at the WTC site, several other linked projects were also underway. In 2006, Mr. Silverstein completed construction of 7 World Trade on land controlled by him and not the Port Authority. A temporary PATH station, largely following the layout of the original, has reopened and is serving approximately 80,000 riders per day during the massive construction project. This temporary station will be replaced with a permanent World Trade Center Transportation Hub, which is being built by PANYNJ, and is scheduled to be completed by 2011. Spanish Architect Santiago Calatrava, designer of the station, said the new station will resemble a bird being released from a child's hand.
Another related project is the demolition of the Deutsche Bank building, immediately across the street from the WTC site. The building was deemed not suitable to reoccupy, or even rebuild, due to the damage and the high level of contamination it incurred after the attacks. Remediation of the contamination there has been delayed. The delays were due, in part, by the sensitive recovery of human remains as well as operations by contractor, Bovis Lend Lease, and subcontractor, Galt. Budget overruns and serious safety problems slowed the clean up process for the contractors. These safety problems culminated in a fire in August of 2007, in which two firefighters were killed. Bovis and Galt were fined almost half a million dollars for safety-related infractions as a result of the fire. Work was allowed to resume at the site with a new subcontractor, LVI, taking over the work.
There are several strands of criticism of the redevelopment project. Some view it as poorly designed for corporate tenants and far too costly overall. Others are critical of the slow pace of the project, which some contend is putting upward pressure on the project’s overall costs. In addition, there are still concerns about the safety of the site and the nearby neighborhoods. Some residents are concerned about the air quality and fear it is being negatively impacted by construction at the site and by dust and dirt being tracked through their neighborhoods by construction trucks. PANYNJ agreed to new dust and dirt control measures as a result of this criticism and insist that air quality measurements show levels of contamination are still below EPA guidelines. However, many residents and workers in the area are still skeptical about the air quality. This skepticism is partly fueled by the feeling among many that immediately after the attack, the EPA did not sufficiently safeguard public health for dangers related to air quality in the surrounding neighborhoods or on ‘the pile’ itself.
Survivors’ Stairway at the World Trade Center to be Moved
Friday, July 18, 2008 | New York Times | Topic: Urban Design & Architecture
A staircase at the original World Trade Center, originally used by survivors of the 9/11 attacks to escape, will moved out of public view for at least four years. The staircase is being relocated to a temporary holding area. It will eventually be placed in the memorial that is planned at the site.
Merrill Lynch Backs Out of World Trade Center Discussions, Again
Thursday, July 17, 2008 | New York Times | Topic: General
Merrill Lynch has ended discussions with the Port Authority of New York and New Jersey and developer Larry Silverstein regarding the company's location to the World Trade Center site. This is the second time that Merrill Lynch has opened and closed discussions. Their current lease, at the World Financial Center, expires in 2013. Informal discussions between the sides have continued according to those involved, in hopes that the company may decide to move in 2018.
Ward: WTC Memorial Will be Ready by 2011
Friday, July 11, 2008 | New York Daily News | Topic: General
Port Authority chief Christopher Ward told attendees at a Community Board 1 meeting on Thursday that the Ground Zero Memorial would indeed be ready by the 10th anniversary of the attacks in 2011. The museum, he noted, would not be ready. The announcement came on the same day that family members of September 11 victims released a letter criticizing Ward’s earlier admission of overly ambitious deadlines and cost overruns. Ward warned that the 2011 deadline for the memorial will be a difficult one to meet.
Families Dismayed By Delays in 9/11 Memorial
Thursday, July 10, 2008 | Newsday.com | Topic: General
15 family members involved in the planning of the September 11th Memorial wrote a letter on Thursday saying that they “do not accept” the fact that it will not be built in time to commemorate the 10th anniversary of the attacks. The families sent the letter to officials who are responsible for the rebuilding of the site.
Lawsuit to Relocate WTC Excavation Dust Turned Down
Wednesday, July 09, 2008 | NY1 | Topic: General
A lawsuit brought on by family members of 9/11 victims to relocate excavation dust from Fresh Kills to a nearby cemetery was turned down by a judge yesterday. The thought is that this dust contains human remains and should be located in a cemetery and not in the dump on Staten Island. The court has supported the relief and excavation efforts the City has made thus far and the case will not be heard.
Former PA Executive Director Questions Integrity of WTC Redevelopment
Tuesday, July 08, 2008 | Gothamist | Topic: Politics & Government
George Marlin, the former executive director of the Port Authority of New York and New Jersey is recommending that federal investigations take place to uncover the reasons for the construction delays of the World Trade Center site. Marlin believes that the delays may be a result of criminal activity such as fraud and deception to investors. However, one source informed the New York Sun that these accusations are false and claimed that the criminal activity described by Marlin would not benefit anyone involved with the redevelopment of this site.
WTC Plans Reconsidered after Delays Announced
Sunday, July 06, 2008 | City Journal | Topic: General
The Port Authority’s announcement last week that the World Trade Center project is both grossly behind schedule and over budget has prompted some to reconsider the plans for the redevelopment. City Journal contributing editor Nicole Gelinas considers the merits of the Twin Towers II Plan, which advocates updating the design and engineering of the original twin towers. The plan was developed by Ken Gardner, a structural engineer, and the late Herb Belton, an architect who worked on the plans for the original towers. According to Gardner, it would be possible to build the new twin towers well under the budget of the current plan, and by the 10 year anniversary of the terrorist attacks on the site.
Officials Face Scrutiny After WTC Report
Saturday, July 05, 2008 | Newsday.com | Topic: Politics & Government
After the stir created by the Port Authority’s report on the schedule and budget problems plaguing the World Trade Center redevelopment, the words and actions of many politicians, both current office-holders and past, are being scrutinized. Current New York Governor David Paterson and Port Authority Chief Christopher Ward are being largely praised for their candor in disclosing details about delays and cost overruns. Meanwhile, former Governor George Pataki faces more pointed scrutiny for setting what Ward and Paterson called unrealistic deadlines and goals. In response, Governor Pataki has said that the aggressive goals were meant to restore people’s faith in lower Manhattan after a tragic and devastating event.
A Call to Privatize WTC Development
Saturday, July 05, 2008 | Other | Topic: General
In response to the Port Authority’s report on the status of the World Trade Center redevelopment, columnist Deroy Murdock suggests that the project should go private. He cites developer and World Trade Center leaseholder Larry Silverstein’s success with the rebuilding of 7 World Trade Center, which was completed less than five years after the terrorist attacks in 2001. Contrary to the arrangement at the ground zero site, where the redevelopment efforts are being overseen by a group of government agencies, Silverstein was able to develop the 7 World Trade Center site with little government interference. Murdoch suggests that the City offer Silverstein the opportunity to develop the ground zero site in a similar fashion.
St. Nicholas Church Rebuilding Struggles Along With Other Projects At World Trade Center Site
Thursday, July 03, 2008 | New York Times | Topic: General
Along with other delays plaguing development of the 16 acre World Trade Center site, the rebuilding of St. Nicholas Greek Orthodox Church has been a struggle. Negotiations with the Port Authority of New York and New Jersey are underway in order to transfer land to rebuild the Church; although there are disagreements over how much the Agency will pay and how large the Church will be. The Port Authority is eager to settle this deal so it can finalize other plans, including the security screening center and the south perimeter wall, which are contingent on what happens with St. Nicholas.
Major Projects on Hold As Cement Truck Drivers Strike
Wednesday, July 02, 2008 | New York Times | Topic: Economic Development
Many major construction projects in the City have now been put on hold due to a cement truck driver's strike. Negotiations were unsuccessful yesterday, causing the union to strike which halted construction on projects already facing delays and budget issues. Continued negotiations are not expected to occur again until after the holiday weekend at the earliest.
WTC Transit Hub Redesign Could Cut Costs
Tuesday, July 01, 2008 | Associated Press | Topic: Urban Design & Architecture
The World Trade Center’s transit hub is facing a redesign after the release of a report stating that the redevelopment of ground zero is not on schedule and has exceeded its budget. According to the Executive Director of the Port Authority of New York and New Jersey, Chris Ward, the wings over the hub, initially intended to open and close, will be stationary. Officials anticipate that this redesign could cut the hub’s budget by hundreds of millions of dollars.
Port Authority Recommends Discarding Old WTC Timelines and Budgets
Monday, June 30, 2008 | Associated Press | Topic: General
In a report released Monday on the progress of development on the World Trade Center site, the Port Authority of New York and New Jersey asserted that deadlines and budgets originally set for the project were unrealistic and unattainable. Christopher Ward, executive director of the Authority, suggested in the report that a committee be formed to set new deadlines, oversee the budget and timeline, and provide more centralized control and decision-making. The committee would consist of representatives from involved government agencies and developers. Ward noted that the Authority was also exploring several ways to cut costs from the project’s ballooning budget.
Port Authority Releases WTC Progress Report: Details Higher Costs and Delays
Monday, June 30, 2008 | New York Times | Topic: General
The Port Authority of New York and New Jersey released a 34-page report on Monday detailing the progress on the World Trade Center site redevelopment. The report notes several challenges that have plagued the project for some time and identifies a number of “fundamental issues” that it says need resolution for progress to continue. Among those issues are problems with the decontamination and demolition of the Deustche Bank Building, which is delaying the start of other projects, and the lack of final plans for several of the large components of the development like the transportation hub and the Vehicle Security Center. The Authority’s board of commissioners met on Monday afternoon to discuss the report’s findings. Several elected officials gave statements in response to the release, most of which were optimistic despite the report’s focus on challenges the project faces.
New Timeline Missing in Latest Progress Report on WTC Reconstruction
Friday, June 27, 2008 | New York Sun | Topic: General
At a Port Authority Board meeting on Monday, the Agency is expected to present a new progress report but it will not have new timeline despite Governor Paterson’s request for an updated schedule of plans. Chris Ward, Executive Director of the Port Authority, is expected to ask for an extension in order to sort out some questions on engineering and design that remain unanswered and will plan to give a full assessment of the status of the project by the end of the summer.
Duetsche Bank Cleanup to be Completed by Year’s End
Friday, June 27, 2008 | Commerical Property News | Topic: General
Avi Schick, Chairman of the Lower Manhattan Development Corporation, the agency responsible for demolishing the Duetsche Bank, announced that cleanup of the site is expected to be completed by the end of this year. A new contractor, LVI Environmental Services Inc., is completing the process. While the original contractor was doing both the clean-up and demolition at the same time, LVI Environmental will complete all the asbestos and mold removal first before deconstruction. The first contractor, John Galt Co, was fired after a deadly fire in August of last year. The LMDC has authorized an additional $37.5 million for the efforts.
Duetsche Bank Demolition Delays Persist
Thursday, June 26, 2008 | WNYC | Topic: General
The Lower Manhattan Development Corporation, the agency responsible for demolition of the Duetsche Bank, announced that delays are likely to continue although their goal is to have the building down by the end of this year. The agency is working to ensure that the asbestos and mold is removed properly. The cost is now estimated to be about $274 million for demolition.
Freedom Tower Starts Taking Shape Above Ground
Thursday, June 19, 2008 | New York Times | Topic: General
The unique shape of the Freedom Tower is starting to become visible at the World Trade Center site as construction continues. The building was designed using the chamfer technique which means that as the building gets higher, the building tapers off at an angle. The first columns to come out of the ground at the site appear crooked to accommodate for this architectural design.
Port Authority May Transfer Freedom Tower to Private Developer
Tuesday, June 17, 2008 | New York Post | Topic: Politics & Government
According to the New York Post, the Port Authority of New York and New Jersey is looking to turn the Freedom Tower over to private developers. While the Port Authority did not comment, sources say that the agency wants to create a “partnership” with a private developer that has real estate development experience. The developer would most likely enter into a long-term lease because the Port Authority owns the land. The developer would continue with the current design for the tower. If such a transfer occurs, it could allow the Port Authority to focus on other projects.
Silverstein Starts Tower 2 Work as Port Authority Finishes Up
Thursday, June 12, 2008 | GlobeSt.com | Topic: General
Silverstein Properties will begin work in the foundation of Tower 2 even though the Port Authority has not completed final construction of the “bathtub”. The Port Authority will have to pay Silverstein fines for every day after July 1st that the work is not finished. However, the Port Authority will not have to pay its contractor $8-$14 million in bonuses had the project been completed on time.
WTC Will Use Alternative Power Sources
Wednesday, June 11, 2008 | Newsday.com | Topic: Environment
UTC Power was commissioned to provide hydrogen fuel cells as one of the power sources for 4 towers at the World Trade Center site, including the Freedom Tower. The fuel cells are "green" energy, they combine oxygen and hydrogen in a chemical reaction which creates water and a clean, renewable power source. It is hoped that the use of such alternative energy will be an example for other major construction projects.
Port Authority Behind Schedule at WTC
Wednesday, June 11, 2008 | Crain's New York Business | Topic: Economic Development
The Port Authority announced today that it will not meet the June 30 deadline for excavation on the site of Tower 2 at the WTC. They project to be done with this part of the excavation by August, however Governor Paterson called for a full audit of the ongoing construction to create transparency in the process. Due to these delays the Port Authority will now owe Silverstein Properties $300,000 per day they run over the deadline. Silverstein Properties will begin work on the foundation of Tower 2 in July despite the delays, however they must work around excavation crews. This is another delay in a string of delays and fines accrued by the Port Authority throughout the rebuilding effort.
Construction to Begin Again on Goldman Sachs Building
Wednesday, June 04, 2008 | NY1 | Topic: Economic Development
With new safety measures in place, developer Tishman Speyer will resume construction on the interior of the first 13 floors in the new Goldman Sachs building in Lower Manhattan. As a result of two serious construction accidents on site, there will be netting in place to prevent materials from causing harm to the surrounding environment. Additionally, construction will not take place during Saturdays of the Little League season.
Freedom Tower Signs International Tenant
Tuesday, June 03, 2008 | NY1 | Topic: Economic Development
The Port Authority of New York and New Jersey signed a contract with the Beijing Vantone Real Estate Company yesterday to lease space in the Freedom Tower. The Chinese development firm expects to rent five floors to house a Chinese business and cultural center. Until yesterday only government agencies had lease agreements for the tower. Vantone is the first private-sector occupant.
Budget Shortfall for Lower Manhattan Agency
Thursday, May 29, 2008 | New York Sun | Topic: General
The Lower Manhattan Construction Command Center (LMCCC), responsible for coordinating development and providing construction oversight of the World Trade Center site and surrounding projects, is facing a $9 million shortfall in its budget because it has not received necessary financing from the state, the Metropolitan Transportation Authority (MTA) and the Port Authority. The city has already contributed. Avi Schick, President of the Lower Manhattan Development Corporation, expects the MTA and the Port Authority to contribute soon.
Could ESDC President's Resignation Affect Redevelopment?
Tuesday, May 27, 2008 | New York Post | Topic: Politics & Government
Avi Schick, president of the Empire State Development Corporation (ESDC) announced to the New York Times that he will resign in September. As chairman of the Lower Manhattan Development Corporation, Schick has been a key player in the redevelopment of Lower Manhattan and in particular, the World Trade Center site. Some believe that Schick’s heavy involvement in this neighborhood has been detrimental to the progress of Ground Zero. Schick, a trained lawyer, may work in the private sector once he leaves the ESDC.
Work at Goldman Sachs Site Stopped Until New Safety Measures in Place
Sunday, May 25, 2008 | Newsday.com | Topic: General
Work at the Goldman Sachs site in Lower Manhattan will not continue until new safety measures are in place. According to Assembly Speaker Sheldon Silver, the company has committed to measures that are above and beyond that required by the City’s building code. The company has also said that they will no longer do any work on Saturdays during little league season. These changes come after a piece of steel fell from the building onto a nearby ball field during a little league game.
Tower 3 Will Likely be Designed to Merrill Lynch’s Specifications
Thursday, May 22, 2008 | New York Daily News | Topic: General
Since Merrill Lynch is now reconsidering a move to the World Trade Center site, the Port Authority says it is looking to design Tower 3 specifically to meet the securities company’s needs. The Authority has granted developer Larry Silverstein a six-month extension on the Tower 3 project so that he can continue negotiations with the possible tenant.
Merrill Lynch Reconsidering A Move to World Trade Center
Thursday, May 22, 2008 | The Wall Street Journal | Topic: General
Merrill Lynch is reconsidering moving into Tower 3 at the World Trade Center site. The company currently holds a lease that will expire in 2013 and the Port Authority is considering delaying constructing on one of the three towers being developed on the site by Larry Silverstein in order for Merrill’s design requests to be made. It is likely that Merrill Lynch will request tax breaks from the city in exchange for its decision to stay in Lower Manhattan.
Port Authority Considers Deadline Change to Facilitate Negotiations with Merrill Lynch
Thursday, May 22, 2008 | New York Times | Topic: General
The Port Authority of New York and New Jersey is considering extending the deadline for Silverstein Properties to build Tower 3 at the World Trade Center site from December 31, 2011 to June 2012 in order to allow Silverstein to negotiate with Merrill Lynch to locate there. It is believed that with the deadline, Silverstein does not have the flexibility he needs to redesign the building to meet the financial company’s needs. The deal would also extend the deadline for Tower 4’s completion till the spring of 2012.
Freedom Tower Structure Reaches Street Level
Monday, May 19, 2008 | New York Times | Topic: Urban Design & Architecture
The Freedom Tower construction reached a new milestone on Saturday when two steel columns were attached to existing jumbo columns, just reaching above street-level. Previously, all construction at 1 World Trade Center had been subterranean. The new achievement did not receive the fanfare of previous ceremonies at the site, but was announced by the Port Authority in a two-sentence statement.
Deutsche Bank Demolition Progresses Slowly
Monday, May 19, 2008 | New York Post | Topic: General
An editorial in the New York Post laments the slow pace at which progress is being made at the Deutsche Bank building in lower Manhattan. The article notes that since the tragic fire at the site last year, there appears to be no progress in the demolition of the “allegedly highly toxic” building. According to a representative at the Lower Manhattan Development Corporation, clean-up of the site will be complete by the end of the year, at which point demolition can begin. The editorial ends with a plea to Mayor Bloomberg to push the project along.
Future of Arts Center at WTC Site Remains Questionable
Monday, May 19, 2008 | Newsday.com | Topic: General
The original plans for the World Trade Center redevelopment by architect Daniel Libeskind included an arts center with two theaters and two new museums. In 2004, four institutions were signed on to occupy the center. Today all but the Joyce Theater have withdrawn from the project and Linda Shelton, the executive director of the Joyce says she is frustrated over continuing delays on the development. Shelton says that she had hoped that construction would have begun by now, but the land needed for the center is currently being occupied by a temporary subway entrance and will not be available until 2011. Plans to move the arts center offsite – possibly to the Fulton Street Transit Center – are still being considered.
Work Halted at Goldman Sachs Building in Lower Manhattan
Sunday, May 18, 2008 | NY1 | Topic: General
Construction was stopped at the site of the new Goldman Sachs building in lower Manhattan on Saturday after an 18 inch piece of steel fell onto a nearby ballfield where children were playing. No one was injured. This is the second serious construction accident that has occurred on the site in the past six months.
Port Authority Working to Avoid Late Fees at WTC Site
Friday, May 16, 2008 | New York Sun | Topic: General
The Port Authority is reported to be in negotiations with developer Larry Silverstein to avoid paying late fees that would be due if they were unable to turn over a ground zero building site by the deadline of June 30. The authority missed a similar transfer deadline for another site at the beginning of the year, resulting in about $14 million in fines. In order to avoid owing more money, the authority is considering allowing Silverstein to enlarge the floor plates of his development in exchange for waiving the fees. A spokesperson for the Port Authority said that they are still working to meet the deadline.
JP Morgan Could Save $3 Billion by Moving to Midtown
Thursday, May 15, 2008 | Reuters UK Edition | Topic: General
The Chief Executive for JP Morgan Chase said that moving its headquarters to their recently acquired Bear Sterns building in midtown would save the company about $3 billion because it would no longer need to construct a building in lower Manhattan at the World Trade Center site. A spokesperson for the Port Authority of New York and New Jersey claims that the Lower Manhattan project is still on.
City Tries to Negotiate out of World Trade Center Deal with Goldman Sachs
Tuesday, May 13, 2008 | New York Times | Topic: Economic Development
In an effort to keep Goldman Sachs in Lower Manhattan after September 11th 2001, the City provided the banking firm significant incentives as well as $320 million in penalties if infrastructure, transit, and security plans were not in place for the area surrounding the former World Trade Center site by 2010. The city is now trying to work out a deal to avoid paying some of those fines, considering the delays the project has faced thus far. The deal given to Goldman Sachs has been criticized by many who see it as a major giveaway to a company that is not in need. Goldman Sachs contends that they wanted this clause in their agreement with the City so that the area did not become a perpetual construction site.
Construction of Underground Tunnel Underway at WTC Site
Thursday, May 08, 2008 | New York Times | Topic: General
The southern section of the No. 1 train tunnel that cuts through the World Trade Center site has been cleared of soil in order to construct an underpass connecting the eastern and western sides of the site. The underpass is being built under a network of steel beams on which the subway now rests. Eventually the entire area under the subway from Vessey Street to Liberty Street will be cleared and will be part of the underground, multilevel structure that will include shops, parking, and a PATH terminal.
Design Alterations to Be Made to WTC Transportation Hub Structure
Thursday, May 08, 2008 | New York Times | Topic: Urban Design & Architecture
The Port Authority of New York and New Jersey plans to reduce the size of the centerpiece structure above the train station at the World Trade Center site. The Port Authority would like to keep the planned “winged” concept, but revisions to original design and building material will be made to keep the project in the $2.5 billion budget.
Clean-up Resumes at Former Deutsche Bank Building
Wednesday, April 30, 2008 | NY1 | Topic: General
The Department of Buildings has removed a “stop-work order” on the former Deutsche Bank building in Lower Manhattan because a new fire control system has been installed. Asbestos clearance will resume and will take place six-days a week. Once all the hazardous materials have been removed, demolition work will be resumed.
Speculation Over New Priorities for Governor Paterson; Moynihan Station Could Get Funding Boost
Tuesday, April 22, 2008 | New York Sun | Topic: Transportation
As Governor Paterson is expected to appoint a new Executive Director for the Port Authority of New York and New Jersey, many are speculating how funding could be shifted away from the redesign of the PATH station at the former World Trade Center site to fill the funding gap needed to proceed with the Moynihan Station project. While this shift of money faces many political hurdles because it is from the federal government, some have said that it would be better utilized if allocated to the renovation of Pennsylvania Station since it has serves many more people daily. Governor Paterson has already offered his support to the Port Authority taking a lead role in the Moynihan Station plans.
Tighter Security Urged at WTC Site
Monday, April 21, 2008 | NY1 | Topic: General
The Skyscraper Safety Campaign, a group made up of families of first responders and victims of September 11th, are urging the Port Authority of New York and New Jersey to step up its security at the World Trade Center site after reports emerged last week that security plans were found in a public trash can. The group is also calling for more publicly documented inspections by the Fire Department.
Community Gets Update on WTC Redevelopment From Port Authority
Saturday, April 19, 2008 | Downtown Express | Topic: Land Use
Community Board members were updated on redevelopment progress at the World Trade Center by the Port Authority. Officials noted that the R/W Cortlandt Street subway station will reopen this fall after being closed since 2005, light sequencing is being done by the Department of Transportation to ease sidewalk congestion near the Vesey Street entrance to the PATH train, and nearby residents should expect to see steel going up on the Freedom Tower soon.
Security Plans for Freedom Tower Found in Public Trash Can
Friday, April 18, 2008 | New York Post | Topic: General
A homeless man found outdated security plans for the Freedom Tower in a public trash can in SoHo. The plans detailed the locations of floor layouts, elevator shafts, air ducts and electrical wiring as well as the location of columns for support and the thickness of concrete walls. The Port Authority of New York and New Jersey has vowed to take severe actions to whoever created this security breach. The Port Authority also said that the plans were not very detailed and are provided to any contractor that is bidding on a project at the site.
Portion of Freedom Tower Foundation Does Not Pass Strength Tests
Wednesday, April 16, 2008 | Associated Press | Topic: General
Tests showed that one of the batches of concrete in the Freedom Tower site foundation would not be strong enough to hold the developer’s goal of 14,000 pounds per square inch. Although the concrete passed strength tests when it was initially poured in December, recent tests showed that it would not withstand the necessary weight. Workers on the site spent the last several weeks removing the approximately 50 cubic yards of bad concrete from the foundation. A spokesman for the Port Authority of New York and New Jersey said that the setback will not affect the construction schedule for the tower. The rest of the concrete foundation has passed the strength tests.
WTC Transit Hub Faces Major Delays and Budget Overruns
Wednesday, April 16, 2008 | New York Daily News | Topic: General
The ground transit hub planned for Ground Zero is facing major delays and budget problems. The station, which includes a canopy designed to look like a dove taking flight, was scheduled to open in 2006, and is now not likely to open until 2013. The project is expected to be nearly $1 billion over budget, according to a federal consultant’s report. The delays in the transportation hub could cause delays in the construction of Tower 2 and Tower 3, because of shared underground infrastructure.
PATH Tent Set to be Removed This Weekend
Friday, April 11, 2008 | New York Times | Topic: General
The large aluminum and fabric tent that has covered the Church Street stairs leading to the PATH train on the former World Trade Center site is being removed so construction can continue on the permanent structure. PATH operations will be relocated to Vesey Street until 2011 when the new structure is expected to be completed. The tent, costing only $275,000, has been in place since June 2007.
Schick Proposes New Location for WTC Performing Arts Center
Thursday, April 10, 2008 | New York Times | Topic: General
Avi Schick, the chief executive of the Empire State Development Corporation and chairman of the Lower Manhattan Development Corporation, has suggested a new plan for the location of the performing arts center intended for the World Trade Center site. Schick has recommended that the center be constructed on top of the Fulton Street subway station, suggesting that the change would cut costs and time. Schick’s proposal would be a departure from the previous plan to have retail above the station. The City’s cultural affairs commissioner, Kate Levin, has told the State that they will review the plans and respond within 30 days. Opponents of Schick’s plan worry that changing the plans may cause further delays in development of the transit center. There are also concerns about the noise and vibrations from the transit center disrupting performances.
Freedom Tower to House Observation Deck
Thursday, April 10, 2008 | New York Daily News | Topic: General
The Port Authority of New York and New Jersey announced that it plans to recreate the observation deck that once topped the World Trade Center. The Authority hopes to hire a developer to manage the design, construction, and upkeep of the deck. The indoor space will be on the 102nd floor of the Freedom Tower and will offer views that may stretch out 50 miles. The total cost of the project is estimated at $610 million and will receive both state and federal money in addition to privately raised donations. The Port Authority anticipates selecting a developer for the project by June of next year and opening the deck to the public in 2012. It was also announced that the September 11 Memorial & Museum had reached its fundraising goal of $350 million.
Governor Paterson Wants to Re-Examine Ground Zero Development
Tuesday, April 08, 2008 | New York Observer | Topic: General
At a speech before the Association for a Better New York, Governor Paterson said that New York needs to “revisit the issue at Ground Zero,” mentioning concerns about delays in constructions. He noted that estimates for the completion of the redevelopment may be off by two or three years. It is unclear exactly what the Governor means by “revisit” considering a great deal of construction has already begun.
Police Checks and Limited Access Streets Likely to Be Used Around Trade Center Site
Sunday, April 06, 2008 | New York Daily News | Topic: General
According to a draft security plan that was obtained by the Daily News, checkpoints, limited access streets and other security measures are likely to be used in Lower Manhattan around the former World Trade Center site. Although the New York Policy Department (NPYD) declined to comment on the specifics of the plan, they did say that their intention is to make the site easily accessible but also safe and secure. Some are concerned that the installation of barriers on many streets will increase congestion and make it nearly impossible to move through Lower Manhattan.
$20 Billion in Development At Risk Due to Slowing Economy
Monday, March 31, 2008 | New York Daily News | Topic: Economic Development
Due to the slowing economy, over $20 billion in development projects in the City could be scaled back, significantly delayed or even killed. The affected projects include Moynihan Station, Fulton Station, Atlantic Yards, Coney Island and the World Trade Center redevelopment. According to Robert Yaro, president of the Regional Plan Association, “We’re not going to throw in the towel on any of these projects, but less dramatic and less expensive designs may be needed.”
JPMorgan Chase Continues to Seek Space in Lower Manhattan
Friday, March 21, 2008 | New York Post | Topic: General
JPMorgan Chase has said that it will continue to seek office space in Lower Manhattan, despite its acquisition of Bear Sterns and the space that that company occupies in Midtown, according to the New York Post. The investment banking company had worked with the Port Authority to develop Tower 5 on the World Trade Center site for its purposes. The company has said that while it will relocate its headquarters to Midtown, it will use the space in Lower Manhattan for other, unspecified purposes. This change will likely alter what the tower is expected to look like, eliminating large trading floors that were expected to jut out of the top floors of the building.
Future Plans for JPMorgan Downtown Uncertain
Thursday, March 20, 2008 | WNYC | Topic: General
At a press conference yesterday, New York City Mayor Michael Bloomberg expressed uncertainty about whether JPMorgan would retain their lease on the Deutsche Bank building at the World Trade Center site. JPMorgan would not say whether or not they would keep the property, which they acknowledged was a valuable property, but said that they would move employees to midtown to the former Bear Stearns building.
WTC Plans Change With JPMorgan Moving Offices Uptown
Wednesday, March 19, 2008 | New York Sun | Topic: Land Use
JPMorgan Chase & Co., which had planned to move its headquarters to the site of the former Deutsche Bank building at the World Trade Center site, has announced that it will instead move its offices into the Bear Stearns building on Madison Avenue as part of JPMorgan’s takeover of that company. The Port Authority is now considering a mixed-use or residential high rise building at the site. The developer, Silverstein Properties, does not think that this change will affect development, and noted that the site had been originally discussed as a residential hotel. JPMorgan is still interested in the site, but will not suffer any penalties if it backs out entirely.
Contaminated CUNY Building Approved for Demolition
Thursday, March 13, 2008 | New York Post | Topic: Environment
After facing several holdups, the US Environmental Protection Agency (EPA) announced yesterday that plans to demolish City University’s Fitterman Hall have been approved. The EPA determined that several contaminants, including asbestos and mercury, need to be removed from the building. The decontamination may take between four and six months and the demolition could take an additional eight to twelve months. The whole process is estimated to cost $16.3 million. An academic building for the City University’s Borough of Manhattan Community College will be constructed on the cleared site and will take approximately two and a half years to complete.
Last Remnants of Former World Trade Center to be Removed from Site
Tuesday, March 04, 2008 | New York Times | Topic: General
The “Survivors’ Stairway” located on Vesey Street is the last remaining remnant of the former World Trade Center site. Construction workers are gearing up to remove the staircase, which was used to help survivors from the North tower get to safety. The staircase will become part of the September 11th Museum that will be opened at the World Trade Center.
New Measures to Control Dust to be Installed at World Trade Center Site
Sunday, March 02, 2008 | New York Times | Topic: Environment
Prompted by residents’ concerns about health hazards, the Port Authority has announced that it will install grates at the entrances and exits of the World Trade Center site in order to reduce the amount of dust that leaves the site and ends up in the surrounding neighborhood. They will also begin using a new street sweeper to help collect the dust that has already left the site. Residents and business owners fear that the dust may be a health hazard, but the Lower Manhattan Development Corporation has said that their tests of the air quality on the site have all shown that contamination levels are below the Environmental Protection Agency’s potentially dangerous level.
Port Authority Cannot Collect Insurance Money from World Trade Center
Tuesday, February 26, 2008 | New York Post | Topic: Finance
A federal judge in Manhattan ruled that the Port Authority of New York and New Jersey is unable to collect insurance money on the destroyed Twin Towers because of its decision to lease the property to Larry Silverstein several months prior to September 11, 2001. Rising costs have been a critical factor in the redevelopment of the area and the amount of insurance money the Port Authority can collect is central to future development plans.
City Agencies May Move to Redeveloped World Trade Center Site
Monday, February 25, 2008 | City Limits Weekly | Topic: Economic Development
The city is trying to work out a 15 year lease deal with Larry Silverstein, developer of the World Trade Center site, to occupy nearly 600,000 square feet of office space on the site. More specifically, the city would like to occupy the 7th - 21st floor of Tower 4 but has not announced which agencies will locate there. Silverstein has until the end of 2009 to act on his option, which would make the deal binding. The city would pay significantly below market rate for the space but would be a tenant that Silverstein could count on.
Security Issues Found in WTC Plans
Sunday, February 24, 2008 | New York Daily News | Topic: General
A New York Daily News investigation has found that some law enforcement officials are concerned about several security weaknesses in the planned World Trade Center redevelopment. Primary concerns are centered around issues with vehicle inspection, the buildings’ proximity to the city streets due to the reinstated street grid on the site, and the abundance of glass used in Towers 2, 3, and 4. The buildings also do not meet certain blast standards set by the Department of Homeland Security or Department of Defense typically used for embassies and buildings overseas and some of the screening technology that is cited in the plans does not yet exist. Officials involved in the development project insist that the site will be one of the most secure in the world.
Abatement is Primary Focus for Duetsche Bank
Friday, February 22, 2008 | Downtown Express | Topic: Land Use
Officials from the Lower Manhattan Development Corporation (LMDC) have said that the abatement work on the former Duetsche Bank site will take more time than the actual demolition of the building. The LMDC is hoping the abatement work will be completed by the fall and demolition started in November.
Huge Fines, Many Violations Found at Deutsche Bank Tower
Wednesday, February 20, 2008 | New York Times | Topic: General
Federal safety regulators at the Occupational and Safety and Health Administration (OSHA) have proposed fining the contractors in charge of the Deutsche Bank tower nearly $500 million for violations that led to last summer’s fire, which killed two firefighters. OSHA found 44 violations that occurred either because of negligence or an intentional lack of concern about dangerous conditions by the contractor, Bovis Lend Lease, or the subcontractor, the John Galt Corporation. Most of the violations were listed as serious, and five were even listed as willful – the most egregious category. The contractors have 15 days to fight the allegations, which they have pledged to do.
Port Authority Hands Over Land to Silverstein at World Trade Center Site
Monday, February 18, 2008 | Associated Press | Topic: Land Use
The Port Authority of New York and New Jersey turned over property on the World Trade Center site on Sunday to developer Larry Silverstein who will build two towers on the land. The handover was nearly seven weeks delayed and will cost the Port Authority $14.4 million in penalties. A third area of land is still under excavation by the Port Authority, but is expected to be turned over to Silverstein by the end of June without any late fees attached.
Safety Chief Hired for World Trade Center Site
Wednesday, February 13, 2008 | Newsday.com | Topic: General
Joseph Schwed has been announced as the new safety chief for the entire World Trade Center redevelopment project. The Port Authority of New York and New Jersey had previously hired safety overseers for each individual project on the site. New safety rules in the city prompted the site owners to hire someone who would be in a position to coordinate safety operations for the entire 16 acre site. Schwed, a former Port Authority employee, will oversee all safety contractors and will coordinate safety requirements between the different projects.
Duetsche Bank Demolition Plan Approved
Thursday, February 07, 2008 | NY1 | Topic:
The Lower Manhattan Development Corporation (LMDC) received approval on Thursday of a plan to complete demolition of the former Duetsche Bank. Under the new plan, abatement will occur first and then demolition. Safety enhancements were also included the amended plan that was approved.
Future WTC Site Starting To Come Together
Friday, February 01, 2008 | Downtown Express | Topic: General
Progress is being made on the massive construction efforts at the World Trade Center site. The construction of the temporary entrance to the PATH station is on schedule to be completed in the next few weeks. Visitors to the site can see the remains of the “Survivor’s Stairway” which served as an escape route for workers on 9/11 and is currently being prepped so it can be moved and put on display in the memorial museum. The excavation of the site of Tower 4 is complete and the site of Tower 3 is nearly complete. The Tower 2 site is scheduled to be excavated and turned over to Silverstein by June 30. Progress on the Freedom Tower is also visible as steel beams and concrete are erected to form the core of the building.
Silverstein Asserts that Financial District is Immune to Possible Financial Market Downturn
Wednesday, January 30, 2008 | Reuters US Edition | Topic: Economic Development
Larry Silverstein, developer of the World Trade Center site, has expressed confidence that the financial district in lower Manhattan will evade any possible downturn in the financial market. He cited the area’s excellent public transportation access, significant investment by non-financial corporations, and commitment from city officials to redeveloping the WTC site and surrounding area as bases for his confidence.
Freedom Tower May Include New Restaurant
Monday, January 28, 2008 | New York Observer | Topic: Economic Development
The Port Authority of New York and New Jersey is considering developing a new restaurant atop the Freedom Tower. The Agency is expected to release a Request For Expression of Interest (RFEI) for potential developers to build and operate a restaurant on the 100th and 101st floors of the new building. They hope to pick a winner by the end of the year. The Freedom Tower is projected to open in 2013.
Fire Official Will Remain on Site at Deutsche Bank
Friday, January 25, 2008 | New York Daily News | Topic: General
A high ranking official with the Fire Department of New York (FDNY) has been asked to remain on the Deutsche Bank site as demolition resumes. A Battalion Chief has been on the site since a fire in August killed two firefighters and has been responsible for conducting inspections every 15 days with another Battalion Chief. When work resumes on the Bank, asbestos abatement will happen first and then deconstruction. Prep work is expected to start on Monday.
Deadline for Deutsche Bank Building Demolition Announced
Wednesday, January 23, 2008 | Newsday.com | Topic: General
A state official announced on Wednesday that the demolition of the Deutsche Bank building will be completed by the end of 2008. Lower Manhattan Development Corporation Chairman Avi Schick confirmed the deadline in a testimony at a City Council hearing about the progress on the demolition. Despite setting a deadline for the completion, Schick was still vague about a specific date for work to resume after an August fire. Since the fire, new measures have been added to the building to ensure the safety of firefighters and first responders.
Work To Begin Again at Deutsche Bank Building
Wednesday, January 23, 2008 | Bloomberg.com | Topic: General
Work will finally resume at the Deutsche Bank building near the World Trade Center site on January 28 for the first time since an August fire at the site killed two firefighters. A subcontractor will begin prep work that will take up to 10 weeks, after which demolition can restart. Avi Schick, the chairman of the Lower Manhattan Development Corp., which holds the property, stated that there is no deadline to complete work but he hoped that it would be finished by the end of the year. City Council Member Peter Vallone said that the delays and lack of a timetable for demolition is “a national disgrace.”
Frustration Expressed in World Trade Center Memorial Delays
Saturday, January 19, 2008 | AM New York | Topic: General
In response to the Port Authority’s announcement that the World Trade Center’s Reflecting Absence memorial will be postponed until 2011, many families of September 11 victims are expressing frustration over the delays. The memorial, which was originally slated for completion in 2009, will be completed in phases, with the plaza’s construction preceding the creation of the reflecting pools.
Noise Mitigation Plan for WTC Site Announced
Tuesday, January 15, 2008 | Metro New York | Topic: General
The Port Authority has announced a noise mitigation plan for the World Trade Center site that will involve stopping loud construction early and soundproofing nearby apartments. Some residents do not feel that the plan goes far enough to decrease noise in all affected buildings.
Delays in World Trade Center Excavation Explained
Sunday, January 13, 2008 | New York Times | Topic: Land Use
As the Port Authority rushes to finish excavation of the former World Trade Center site to make way for new towers, it has been criticized for bureaucratic delays. However, the Authority contends that the bedrock and land that they have encountered could only have been identified once the digging process began. The sheer volume of the site and the new depths that must be reached to build foundations have also contributed to the delays in the project.
Port Authority Completes Excavation of WTC Tower 4 site
Friday, January 11, 2008 | New York Observer | Topic: Land Use
After missing its January 1st deadline, the Port Authority announced the completion of excavation of the Tower 4 site. Excavation of the Tower 3 site is slated to be completed by mid-February. Silverstein Properties is responsible for building Towers 2, 3, and 4. The site will be developed into a 64-floor tower designed by architect Fumihiko Makia. Construction crews removed 300,000 tons of concrete, soil and rock as part of the excavation efforts for the sites of Towers 3 and 4.
Investigation of Deutsche Bank Finds Possible Taxpayer Rip Off
Thursday, January 10, 2008 | New York Post | Topic: Economic Development
The New York Post has reported that several thousands of tax dollars assigned for the demolition of the Deutsche Bank may have been “ripped off.” Investigators believe that wire transfers to “shell” businesses were used for illegal payoffs and kickbacks. The Manhattan District Attorney (DA) and the city are currently investigating this and a grand jury has been meeting to hear the information regarding both this and the fire that occurred over the summer. According to sources, the DA's presentation could take several months to finish.
Demolition Expected to Restart at Deutsche Bank Building
Wednesday, January 09, 2008 | New York Times | Topic: Land Use
The demolition of the Deutsche Bank building at 130 Liberty Street is expected to resume shortly. The Lower Manhattan Development Corporation has settled controversies with Bovis Lend Lease, the construction manager. Additionally, a new subcontractor, LVI Services Inc., has been hired to replace the John Galt Corporation. The demolition could take a year and may further delay construction at the site.
Westfield to Run Retail Operations at World Trade Center Site
Monday, January 07, 2008 | GlobeSt.com | Topic: Economic Development
The Westfield Group has entered into a letter of intent with the Port Authority to run the retail operations at the former World Trade Center site. Under the agreement, the


